Customer Issues
- Life saving highly-portable ventilator technology with 100X surge demand created immediately due to the Covid-19 pandemic
- Customer’s supply chain and production capacity was insufficient to meet demand for 100,000+ ventilators to be produced in 3-4 months, and a major contract under the Federal Defense Production Act
- Customer’s suppliers traditionally providing lower volume and one-off jobs, lacking engineering expertise, materials and processes to support rapid launch and high- volume production rates needed
- High Stakes: Every day of delay in delivering a ventilator to doctors meant there were potential lives being lost
The AWT Solution
- Full Portfolio coverage of functional components, labels, tags and booklet products for the ventilator product and manufacturing operation
- Rapid in-house design support and materials testing to meet product requirements.
- Part launch time compressed to under 2 weeks using accelerated process and material commonization
- Rapid scale-up to full production volumes in under 3 weeks to support greenfield facility supplying 80,000 ventilators
- Supply planning integration with customer’s rapidly developing operating system and highly volatile demand forecast